New gas engine power station is in operation on Untygeyskoye oil field.

The station was constructed under turn key contract by Energoteh Ltd. (Moscow). It consists of three Waukesha VHP5904GSID gas engine power plants rated at 1 MW each. They operate on base mode and generate electric power for the needs of field infrastructure. The main and auxiliary equipment of the station are installed in six all-weather containers.
The station is managed by control system developed by Energoteh on the base of EnergoSoft hardware-software complex. It gives the opportunity of remote control and monitoring of all operating parameters of the station.
The main fuel is casing-head gas (WKI index – 54). Gas treatment system is installed in separate container. The systems includes filter-separator for fuel gas purification, final filter, flow rate meter, and casing-head gas heating unit.

Дата публикации: 
19.07.2010
Хранить в архиве: 
Xранить