Three Solar Turbines Inc. gas turbine power plants were put into operation on Tedinskoye oil field.

Three Solar Turbines Inc. gas turbine power plants were put into operation on Tedinskoye oil field. Electric output of Centaur GS40 is 3.5 MW, thermal output – 6 MW. Earlier 5 gas turbine power plants were commissioned on the station. The plants operate on casing-head gas with hydrogen sulphide content of 1.22 g/m3. Fuel gas treatment unit was delivered by Technofrigo (Italy) and designed around Grasso screw compressors. Generated thermal power is used for technological process of oil dehydration.
Delivery of the equipment, installation works and commissioning were carried out by Energoteh. General designer of the project is NIPIKBS-KOM Ltd.