GE Energy commissioned two MS5001 power plants on Vankorskoye oil field.

Cogeneration gas turbine power station was put into operation under the contract signed with Rosneft. Its total output is 200 MW. General contractor and designer o the project is Energokaskad JSC.
The first stage of the project includes four MS5001 gas turbine power plants and waste-heat boilers manufactured and delivered by REMKO JSC. The main fuel for the station is casing-head gas. Generated thermal power will be used for technological needs of the field. The rest two power plants commissioning is planned in the end of 2010.