Modular Boiler Systems Ltd. built CHP station in Bykovo settlement in Volgogradskaya Region.

MWM TCG2020V12CHP station with electric and thermal output of 4800 kWwas built under the contract with Bykovogas Company. The station consists of four MWM TCG2020V12 gas engine power plants each rated at 1200 kW. The project was realized by Modular Boiler Systems Ltd. on turn-key basis.
Container for BykovoGas CompanyContainer power plants operate on the base mode in parallel with each other. Waste heat utilization system consists of two Viessmann Vitoplex 100PV1 hot water boilers equipped with Wieshaupt burners. All generated electric and thermal power is used for the needs of industrial complex for the extraction and processing of gas and gas condensate.