Full-scale testing of combined cycle power station on the site of Dyagilevskaya TETs (Ryazanskaya Region) was finished

Siemens SGT-800

The testing was continuing during 72 hours. In result all parameters of the equipment were confirmed. The commissioning of the station is planned in 2017. The station consists of two SGT-800 gas turbine power plants each rated at 45 MW with electric generators, heat-recovery steam generators and SST-400 steam turbine supplied by Podolsky machine-building plant with electric generator.