New gas turbine power station is under construction on the site of Central boiler-house in Elabuga (Tatarstan). Commissioning of the station is planned in II quarter of 2018. The station consists of four Taurus 60 GS (Solar Turbines Inc.) gas turbine plants each rated at 5.6 MW and four waste-heat boilers. Total electric output of the station is 23 MW. General designer of the station is Tatbelenergoproject Ltd.

Under the project all eight EGES-12S gas turbine power units were commissioned on the site Yaraktinskoye oil and gas condensate field. Power plants were manufactured and supplied by UEC-Aviadvigatel JSC. Power equipment was installed on two production sites. Total electric output of the first station is 24 MW. It generates electric power for the needs of fuel gas treatment unit. Second gas turbine power station has electric power output of 72 MW. It generates electric power for the needs of oil treatment unit. Two last power plants were commissioned on the site at the end of 2017. General contractor for the project is Energoservice engineering center.
PJSCRN-Burenie company bought 33 diesel power plants manufactured by PSM. The plants each rated at 320 kW were supplied for operation on the sites of the fields in Krasnoyarsky and Krasnodarsky Areas and in Khanty-Mansiysky Autonomous Area. Diesel power plants will operate as stand-by plants and will provide electric power for the needs of drilling equipment - boring winches, rotors and pumps. They also can operate as base load power plants and generate electric power for new rotational villages.