Power unit № 2 was put into operation on the site of Tyumenskaya TETs-1 power station.

It is the first project commissioned under Fortum investment program. The power unit was developed on the base of combined cycle power plant. Electric output of the plant is 230.5 MW, thermal output – 292.7 MW.

It was designed around Ansaldo Energia V64.3A gas turbine rated at 77 MW. The supplier of main power equipment is Power Machines JSC. Total efficiency of the plant is 63 %, heat rate – 85 %. Two more gas turbine power plants each rated at 255 MW will be installed on the site of Tyumenskaya TETs-1 till 2014.